- ADP No : 172-190183
- Project Name : SETTLEMENT AND DIGITIZATION OF LAND RECORDS IN DISTRICTS DIR LOWER, DIR UPPER AND TEHSIL KALAM (SWAT)
- Approved Cost : PKR 1,931.089 Million
- Revised Cost : PKR 2,483.762 Million
- Total Area : 7,452 Sq.km
- 1st Administrative Approval : 20, December, 2020
- 2nd Administrative Approval : 10, October, 2025
- Project URL : www.slrdirkalam.com
- Authority Responsible : Board of Revenue, Revenue and Estate Department, Government of Khyber Pakhtunkhwa
- Sponsoring : Government of Khyber Pakhtunkhwa
- Execution : Board of Revenue, Revenue and Estate Department, Government of Khyber Pakhtunkhwa
- Operation and Maintenance : Board of Revenue, Revenue and Estate Department, Khyber Pakhtunkhwa
Project Locations and Area Statistics
| Sr.No | District | Sub-division | Area | Population | No of Households |
|---|---|---|---|---|---|
| 1 | Dir Lower |
Timergara | 1,597 |
1,435,917 |
155,338 |
| 2 | Samarbagh | ||||
| 3 | Chakdara | ||||
| 4 | Lal Qila | ||||
| 5 | Dir Upper |
Dir Khas | 3,752 |
946,921 |
120,228 |
| 6 | Wari | ||||
| 7 | Sheringal | ||||
| 8 | Swat | Behrain (Kalam) | 2,103 | 84,484 | 9,810 |
| Total | 7,452 | 2,467,322 | 285,376 | ||